Science Research Time-Line*
|
Date |
Project Component |
|
9.11 |
Topic Selected |
|
9.18 |
2 Papers read and Reviewed |
|
9.25 |
4 Papers read and Reviewed |
|
9.29 |
6 Papers read and Reviewed |
|
10.2 |
Research Plan outline |
|
10.9 |
Introduction and Literature Cited completed |
|
10.16 |
Methods completed |
|
10.23 |
Revisions completed and SRC Power point |
|
10.23-11.13 |
Experiment |
|
11.20 |
Data Analysis Complete |
|
11.23 |
Rough Draft of Paper |
|
12. 4 |
Final Draft of Paper (midterm exam component) |
|
12. 11 |
Abstract |
|
12. 18 |
Forms Complete…submission to RPI |
|
1.4-2.10 |
Poster work |
|
2.11 and 2.12 |
Construct Poster and presentation |
|
3.20 |
RPI 6:45 AM to 6:30 PM |
|
6.6 |
Greenwich Science Symposium 7PM- 9:30 PM (final exam component) |
*Please note that these dates are all deadlines...when that part of your research project should be completed